Fort White Elementary School
K-12 Education · Ft. White, FL · Construction Management at-Risk
Project Overview
Construction of a 24,000 SF New Classroom and Administration Building on an existing Elementary School Campus. Final GMP: $8,824,194. The project was allocated 390 days with 0 days added by change order and 0 days late at completion. Actual days for completion: 400 days. Contract time adjusted per requests to use Contingency Funds.
Scope of Work
Construction of a 24,000 SF New Classroom and Administration Building on an existing Elementary School Campus. Change Orders: Owner Direct Purchase Items and Contingency Authorizations. Self Performed Work: Project Management, Supervision, General Labor.